Aluminium Shopfront, Curtain Walling, & Windows, Ayr

Project Name

Aldi Ayr

Project Challenge

Remove all existing screens, manufacture & install complete glazing envelope within 7 weeks of placement of order.

The Solution

Manufacturing drawings sent for approval and agreed with the architect within 5 days of order and site measure, fast track procurement of framing from Senior Architectural consisting SCW Curtain Walling, SFG Shopfront Framing, SD Series Doors, & SPW 300 Windows. Fabrication and installation of over 180m2 of glazing, within 3 weeks of receipt of raw materials.

The Result

Another Aldi project opened on time and on budget.